Thruway Authority to Continue Tappan Zee Bridge Deck Replacement Project
ALBANY, NY (06/26/2009)(readMedia)-- The New York State Thruway Authority announced deck replacement work on the Tappan Zee Bridge will continue the week of June 29, 2009.
On Monday, June 29 through Friday, July 3, installation of new modular joints in the main span and the west deck truss will continue in the center lanes.
All work is weather-dependent and subject to change.
Updates will be issued announcing any change in schedule. Lane closures during this operation:
Monday, June 29 through Wednesday, July 1
Work will begin at 8 p.m.resulting in the closure of two left southbound lanes, with an additional left southbound lane closing at 10 p.m., until 6 a.m. from Interchange 10 to the east deck truss on the Tappan Zee Bridge.
These lane closures are for the installation of new deck joints in the center lanes main span and west deck truss. All lanes are expected to be open by 6 a.m. the following day.
During Monday through Wednesday nights' operations, two left lanes in the northbound direction from Interchange 8 to milepost 13 will also be closed from 10 p.m. until 6 a.m. as part of this work.
Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 10 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119. All lanes are expected to be open by 6 a.m. the following day.
Thursday, July 2
Work will begin at 9 p.m.resulting in the closure of the left northbound lane, to three northbound lanes at 11 p.m., to four northbound at 1 a.m. until 6 a.m. from Interchange 8 to the east abutment on the Tappan Zee Bridge.
These lane closures are for the installation of new deck joints in the center lanes main span and west deck truss. All lanes are expected to be open by 6 a.m. the following day
During Thursday operations, two left lanes in the southbound direction from Interchange 11 to east abutment will also be closed from 9 p.m. until 6 a.m. as part of this work.
Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119. All lanes are expected to be open by 6 a.m. the following day.
Friday, July 3
Work will begin at 10 p.m.resulting in the closure of the left northbound lane, to three northbound lanes at 11 p.m., to four northbound at midnight until 8 a.m. from Interchange 8 to the east abutment on the Tappan Zee Bridge.
These lane closures are for the installation of new deck joints in the center lanes main span and west deck truss. All lanes are expected to be open by 8 a.m. the following day
During Friday night's operations, two left lanes in the southbound direction from Interchange 11 to east abutment will also be closed from 10 p.m. until 8 a.m. as part of this work.
Due to the northbound lane closures, the entrance ramp from Broadway (southbound) in Tarrytown will also be closed from 10 p.m. until 8 a.m. All traffic will be detoured to the entrance ramp from Route 119. All lanes are expected to be open by 8 a.m. the following day.
Saturday, July 4
There is no work scheduled.
For the safety of the public and construction workers, motorists are urged to proceed with caution and obey posted work-zone speed limits. Work will proceed weather-permitting, and schedule updates will be announced as needed.
Traffic updates will be broadcast to motorists via Dynamic Message Signs along the highway and by Highway Advisory Radio, 530 AM in the Tappan Zee Bridge corridor, as well as 1610 AM in the Newburgh area.
Weather permitting, the deck replacement project is slated for completion in Fall 2009.
-30-
The Authority offers a free email service called TRANSalert to its customers via email or text messaging to inform them of major unscheduled incidents that may affect their travel on the Thruway. To sign up for the TRANSalert service, customers can visit the Authority's website at www.nysthruway.gov/tas/.
Want to create your own news and distribute it in minutes?
News From

New York State Thruway Authority
Contact Information
- Office of Media Relations & Public Affairs, 518-436-2983
Share this News
Recent News
- Thruway Authority to Continue Tappan Zee Bridge Deck Replacement Project
- Thruway Authority Announces Brief Traffic Stops Near Interchange 28 (Fultonville)
- Authority Announces Lane Shifts for 15-mile Reconstruction Project between Interchanges 39 & 40 Set to Resume
- Thruway Authority Announces Ramp from Scajaquada to I-190 Southbound to Temporarily Close Beginning March 19
- Thruway Authority Announces Rolling Road Block For Reconstruction in Syracuse Area This Afternoon
- Tappan Zee Bridge Repairs To Continue
- Thruway Authority Announces Westbound Motorists in Syracuse impacted by Rolling Road Block Thursday, March 18
- Repairs to Tuckahoe Road Overpass on I-87 to Necessitate Lane Closures
- 2nd Traffic Update for Newburgh-Beacon Bridge Accident
- Traffic Advisory Update for Newburgh-Beacon Bridge
- TRAFFIC ADVISORY - ACCIDENT NEWBURGH-BEACON BRIDGE TOLL PLAZA